Opening Spring 2016
Gateway Shopping Center
221 East Swedesford Road Wayne, PA
Check back for weekly updates
June 2, 2016
Framing has started!. The framing of the offices and bathrooms is scheduled to be completed by the end of the week. Electric and plumbing starts Monday! Electrician is scheduled to complete scope of work in 5 days. Plumber in 2 weeks.
May 19, 2016
Demolition complete! Rough plumbing scheduled to be completed by the end of the week with framing going up next week.
The space looks CRAZY BIG now that everything is out. The picture below is only half the space and the door on the right is 8' high, just for reference....